In January 2021, our Development Management Committee approved the plans for the older persons' care home on Hockliffe Road in Leighton Buzzard. Work to redevelop the site of the former police station started in September 2021 and completed in December 2024.

Development Timeline

February 2025

Occupation

Completion is estimated to be 2024
-->

December 2024

Completion

Meeting to discuss development of the SEND Partnership Programme and specifically the development of engagement with parents and carers.
-->

June 2022

Plans for care home and independent living scheme approved

Progress update to Children’s Services Overview and Scrutiny Committee.
-->

January 2021

Detailed planning application submitted

View planning application
-->